Plan a custom linen order backwards from the date you need the clothing at home. LINENELLAR’s usual estimates are 7–14 days for making after the specifications are confirmed, followed by 7–14 days for standard transit. The time spent choosing a design, checking measurements and approving the brief comes before those stages.
Choose an arrival date before the occasion
For travel, use a date before departure so you can try the outfit with your shoes, check the agreed details and pack it. For an event, leave the personal margin you need for inspection and preparation. An arrival target of the event morning gives you little room to respond to a delay or a fit question.
Send the destination and required arrival date with the initial product enquiry. A multi-person order or a substantial design request needs its own feasibility check; an individual-order estimate does not reserve capacity for a larger project.
A worked calendar, with the assumptions visible
The following dates are a planning example, not a promised delivery or a reserved making slot. Imagine an event on 30 June and a personal target to receive the outfit by 23 June.
| Planning point | Illustrative date | What it means |
|---|---|---|
| Event | 30 June | The outfit is needed for use |
| Preferred arrival at home | 23 June | Seven days of personal margin |
| Final specification approved | 26 May | 28 days before the arrival target |
| Making, allowing 14 days | 26 May–9 June | Uses the longer end of the usual making estimate |
| Standard transit, allowing 14 days | 9–23 June | Uses the longer end of the usual transit estimate |
| Enquiry and decisions | Before 26 May | Not included in the two making/transit ranges |
This example uses calendar-date arithmetic only. It leaves no extra time inside the two 14-day stages for disruption, customs or a revised brief. If those risks matter to your deadline, start earlier and ask about the actual service and capacity. The studio’s order-specific confirmation should be the schedule you rely on.
Recalculate when approval moves
If that example’s final brief is approved on 2 June instead of 26 May, the same 28-day planning allowance reaches 30 June. The seven-day personal margin has disappeared. Keeping the original event date in a message does not make the lost time reappear.
The useful response is to revisit the whole order: can the existing design and confirmed capacity meet the requirement, is an appropriate express service available, or is the deadline too tight? Do this before paying rather than assuming the workshop can shorten production to compensate.
Express changes the journey, not automatically the making
Express transit is estimated at 5–7 days where an appropriate service is agreed, with a separately quoted fee. It does not automatically shorten the 7–14-day making stage. The route, parcel and arrival requirement still need checking.
Standard shipping is free within Vietnam and USD25 per international order under the current policy. Destination import charges are a separate point to clarify. Read the shipping information alongside the item total.
Send a brief that can be scheduled
Product/design: ___; quantity: ___
Destination area/postcode: ___
Event or departure date: ___
Preferred arrival at home: ___
Measurements and colour ready for review: yes / outstanding details listed below
Express quote needed: yes / no
Use the custom service or contact LINENELLAR while there is still time to resolve the unanswered details.